Project Updates 

green-checkmark Land secured

green-checkmark Title V air permit extension (construction/operating) received from LDEQ

green-checkmark St. James Parish Planning Commission approval received

green-checkmark Front end engineering design is nearing completion and based on an existing plant with demonstrated high reliability

green-checkmark EPC lump sum turn key proposal under review; in process of refreshing bid due to price benefit from oil market downturn

green-checkmark Firm natural gas supply secured

green-checkmark Firm natural gas transport secured

green-checkmark Louisiana state tax abatement package secured

green-checkmark Independent engineer’s report identified no high risks to lenders